Investor: Municipal Water And Sewage Company in Warsaw,
Substitute Investor: ZBM
Start: September 2013
Completion: October 2014

Works included:

Section 1 - Trakt Lubelski street on Kadetów –  Zwoleńska str. section
Construction of road drainage and DN 200 water supply reconstruction.

 

Section 2 – Zwoleńska street on the Trakt Lubelski str.–  Rogatkowa str.

450 meters of DN 300 sewage in microtunelling method with street drainage. Within the contract the following works have been executed: 146 inlets, 65 sewage wells, approx. 1 km of different diameters sewage pipeline and 100 meters of DN 200 water supply.

Due to the new roads construction, the water supply equipment have been leveled (170 valves and water hoses) together with 140 different size sewage wells.

 

 

 

MELIORANT 

 

 

Tadeusz Zając i Spółka sp.k.

 

 

ENGINEERING CONSTRUCTION

NOTE! This site uses cookies and similar technologies.

If you not change browser settings, you agree to it.

I understand

x